Long-term Infrastructure Plans

Village infrastructure long-term plan as adopted in April of 2007:

I. Sidewalks

2007: Michigan St. - Church driveway north to end of cemetary

2008: Oakmount Ave. - Hillcrest to #23, Elm St. - #10 to #14

2009: Main St. from Michigan St. to ARC home

2010: South Ave., east side to Village line

2011: Elm St west side to Village line

II. Gutters

2008: Park Place - east and north side

2010:Hillcrest


III. Piping

2008: Park Place

2010: Hillcrest Dr.

IV. Streets - oil and stone

2007: Main St., Michigan St., South Ave. (north of state St) Hillcrest Dr.

2008: Page Place, Oakmount Ave., South Ave, Jones Terrace, Park Place.

2009: E Main St., Bennett Ave., Howard Ave., Park Place, South Ave.

2010: Michigan St, Hillcrest

Resurface:

2008: South Ave (North and south of 5&20)

2015: Church St

2019: E Main St, Bennett Ave, Jones terrace

2022: Oakmount, Hillcrest, Howard

2024: Page and Park Place

2025: Michigan St

2026: Main St


V. Water improvements


2007: clean up brush/grass at both well houses

          install 200 meters

         Elm St line replacement

2008: drill new well at Michigan St., install 250 of 450 new meters

2009: Park Place waterline extension, install balance of new meters


VI. Sewer improvements


2007: clean area around sewer plant
          install new sand fiter valves
          install new sewer pumps
          primary clarifier skirting
          sewer line testing

2008: blacktop WWTP around old buildings