Long-term Infrastructure Plans
Village
infrastructure long-term plan as adopted in April of
2007:
I. Sidewalks
2007: Michigan St. - Church driveway
north to end of cemetary
2008: Oakmount Ave. - Hillcrest
to #23, Elm St. - #10 to #14
2009:
Main St. from Michigan St. to
ARC home
2010: South Ave., east side to
Village line
2011:
Elm St west side to Village line
II. Gutters
2008:
Park Place - east and north side
2010:Hillcrest
III. Piping
2008: Park Place
2010: Hillcrest Dr.
IV. Streets - oil and stone
2007:
Main St., Michigan St., South Ave. (north of state St)
Hillcrest Dr.
2008:
Page Place, Oakmount Ave., South Ave, Jones Terrace,
Park Place.
2009:
E Main St., Bennett Ave., Howard Ave., Park Place, South
Ave.
2010:
Michigan St, Hillcrest
Resurface:
2008:
South Ave (North and south of 5&20)
2015:
Church St
2019: E Main St, Bennett Ave,
Jones terrace
2022:
Oakmount, Hillcrest, Howard
2024:
Page and Park Place
2025:
Michigan St
2026:
Main St
V. Water improvements
2007: clean
up brush/grass at both well houses
install 200 meters
Elm
St line replacement
2008: drill new well at Michigan
St., install 250 of 450 new meters
2009:
Park Place waterline extension, install balance of new
meters
VI. Sewer improvements
2007: clean area around sewer
plant
install new sand fiter valves
install new sewer pumps
primary clarifier skirting
sewer line testing
2008:
blacktop WWTP around old buildings
back
|